- System Integration Design for a Small Hydropower Plant at Rrapun river, Librazhd, Albania, with a small diversion dam with 4 radial gates, powerhouse hosting 3 Francis Turbines coupled with 3 generators 6.3KV / 3.4MW, and a High Voltage Substation 6.3/ 110KV.
- Execution of electrical installation works in Powerhouse and Dam
- Design, procurement and Installation of Project Wide Ethernet Network over Fibre Optics Ring IEC-61850.
- Design, Manufacturing and Installation of Generators’ Exhaust System Automation. Design, Supply and Installation of CCTV system with 13 special outdoor cameras over IP.